Estero Boulevard Improvements Project, Segments 5-6

Project Photos

More

Overview

The Estero Boulevard Improvements Project is a multi-phased project consisting of six (6) one mile segments. Segments 5 and 6 spans from Albatross Street to Estrellita Drive. The scope of work includes installing a new force main, new center lane storm drainage system, sidewalk improvements, trolley stop locations, center drainage pavers and a complete rebuild of the roadway from right-of-way to right-of way, maintenance of traffic (MOT), striping and paving.
Start Date
07/02/2020
Est. Completion Date
03/22/2022
Construction Costs
$18,912,725.29
Owner
Lee County
Construction Manager
Chris-Tel Construction

Construction Status

45%

Subcontractors

NameTypeWebsite
AA Surface Pro, Inc.
Surveying and Mapping
Website
Ajax Paving Industries of Florida, LLC
Paving
Website
American Infrastructure Services, Inc.
Traffic Control
Website
Cella Molnar & Associates
Public Information Officer
Website
GFA International Inc.
Geotech Engineering
Website
McShea Contracting, LLC
Pavement Markings
Website
Passarella & Associates, Inc.
Environmental Consultant
Website
Tincher Concrete
Concrete / Pavers
Website